For architects, engineers and design managers: whatever the documents leave unresolved gets resolved on site, under pressure and usually at someone else’s cost.
It’s three weeks before the basement pour. An RFI lands: the waterproofing clause says “integral system or approved equivalent”, the pile cap junction hasn’t been resolved for the specified system, and nobody can find a compliance statement for the certifier.
Nobody did anything wrong. The design team was working to a tight fee and a moving brief, and concrete protection was one small line in a big package. Now that small line risks holding up a pour, the programme and the warranty position.
Every project gets built twice: once on paper, then on site. Any gap in the first build gets filled in the second, where it costs more.
Why concrete protection gets left loose
Waterproofing, curing, sealing and surface hardening sit between disciplines. The structural engineer owns the concrete, the architect owns the finish and the trade package owns the application. It’s easy for each to assume someone else has resolved the detail.
- RELATED READING: Why Preconstruction and ECI Definitely Matter
The gaps tend to show up in three places.
1. Open-ended clauses
“Or equivalent” invites substitution at tender. Two systems can sit in the same category and still differ materially in performance, application requirements, interfaces and warranty conditions.
2. Unresolved details
Construction joints, penetrations and transitions between systems are where water finds its way in. Standard details rarely cover them, so the decision falls to whoever is on site that day.
3. Missing paperwork
Technical data, compliance statements and EPDs (Environmental Product Declarations, independently verified reports of a product’s environmental impact) are often chased at the last minute, or at handover.
![]() |
The MARKHAM approach: resolve it in the documents
The fix is to treat concrete protection as a designed element, with supplier input before the specification is issued rather than after the tender closes.
MARKHAM supports design teams in three practical ways:
- Ready-to-use documentation. System specifications, standard details and supporting technical, compliance and environmental documentation, available in our Reference Library.
- Project-specific detailing review. Our technical team reviews your details, checks compatibility with surrounding systems and helps integrate ours into the full specification.
- Constructable methods. Simplified methodologies and a clear construction sequence, so the design intent survives the trip to site.
That support covers our waterproofing, curing and surface hardening ranges.
There’s one more advantage. MARKHAM can offer a supply-and-apply service, with its own experienced crews. The team that helps resolve the detail is also accountable for implementing it.
-
- ON THAT TOPIC: Powerful End-to-End Delivery
An Example In Practice
On the New Dunedin Hospital basement, MARKHAM worked with the design team before construction to resolve waterproofing detailing, establish the specification and provide the required technical documentation before works commenced.
![]() |
Before issuing the specification, ask:
- Is the required performance clearly defined?
- Are joints, penetrations and interfaces actually resolved?
- Is the supporting technical and compliance documentation available?
If any answer is unclear, resolve it before tender, not during construction.
Documenting concrete waterproofing, curing or surface protection?
Whether you’re documenting a basement, podium, car park, industrial floor or exposed slab, MARKHAM can review your concrete protection details and specification before they go to tender.
Send MARKHAM your drawings or specification and our technical team can review:
- proposed system selection
- interfaces and transitions
- project-specific detailing
- supporting technical documentation
- construction methodology considerations
- specification wording
Request a specification review!