Data Centre Generator Yards
Location:
Groningen
Country:
The Netherlands
Project Type:
Data Centres | Commercial
Project Scale:
5,001 – 10,000 m²
Adding Life to Concrete – How MARKHAM applied hydrogel systems to the Generator Service Yard areas at a new Data Centre in the Netherlands.
OBJECTIVE
MARKHAM were tasked with providing a treatment process for the new concrete slabs forming Generator Yards at a new data centre. This was to increase the effective cover, enhancing the durability and increasing the lifespan of these slabs and, probably most importantly, protecting the concrete slabs against weathering and rainfall that these areas will be subject to.
SOLUTION
The MARKHAM system put forward to achieve these goals was the spray application of AQURON 2000. This retro spray application provides surface densification and effective cover enhancement with the product penetrating up to 125mm into the concrete. This remains within the substrate for the lifespan of the concrete, providing a durable, maintenance free surface.
RESULTS
The application of AQURON 2000 was a very rapid and cost-effective solution for cover enhancement and concrete densification for the areas treated.
With construction work by other trades continuing in these Yard areas, the application of AQURON 2000 was carried out simultaneously, with pedestrian traffic across the treated areas carrying on within a few minutes of application. Application to the concrete was also carried out beneath the Generator Support Framework without the requirement to remove any of this existing steelwork.
This meant that these areas were successfully treated with next to no impact on other contractors works and this in turn meant there was no negative impact on the overall construction schedule.
With this depth of penetration, the AQURON 2000 is present within the matrix of the concrete for the lifespan of the concrete, making it a maintenance free solution that won’t require any further applications.
Download the Data Centre Generator Yards case study in PDF format.
This and more case studies are also available for download in our library.
|
Project Details – Data Centre Generator Yards |
|
|
Description |
Concrete Generator Service Yards requiring effective cover enhancement and surface densification to increase durability and resistance to weathering and rainfall. |
|
Area Treated |
9,270m² |
|
Age of Structure |
New (2024) |
|
Requirements |
|
|
Operation Downtime / Interruptions |
All areas were treated while construction work was proceeding and as the areas could be put back into use immediately. As a result the application works had minimal negative impact on the project schedule. |
|
Application Method |
|
|
Proposed Further Works |
No further works required. |
|
OHS Requirements |
|